DigitalShift – TechUpGrowth Digital Transformation Initiative

Faculty of Higher Education

Group Assignment Cover Sheet



Unit

Details

Unit Name

IS Project Management

Code

HI5029

Year

2024

Trimester number

T2



Assessment

Details

Assessment Name


Due Date: dd/mm/yyyy




Group Number





** only list students who have contributed to this assignment

Group

Details

Student ID

First Name

Family Name

Contribution %



















Group

Submission

Declaration

Integrity Declaration

We have read and understand academic integrity policies and practices and our assessment does not violate these.


Student ID

First Name

Family Name















Submission Date


Executive Summary

The report explains the project plan for DigitalShift by TechUpGrowth to help the company towards digital transformation by creating a vision for ease of operations and enhancement in customer experience through advanced technologies. This includes implementing an ERP system, mobile application development, enhancement of cybersecurity, and transition towards cloud solutions.

Initiate the 18-month project with a budget of $10 million into an agile project management methodology for flexibility in the following phases: initiation, planning, execution, monitoring, and closing. This report discusses all vital management plans are scope, schedule, cost, quality, resources, and risk management, setting Focus on system integrations, resource allocation, and mitigations of risks. It addresses maintaining operational viability, technical integration, and employee acceptance. This report ensures that TechUpGrowth attains its strategic objectives with the least disruption by adhering to an agile methodology with detailed planning.





Introduction

This report aims to give in detail the project management planning of the DigitalShift initiative, developed by TechUpGrowth. DigitalShift is a huge digital transformation project for its operational efficiencies, better customer experiences, and business outcomes. This project is important to help TechUpGrowth remain competitive in the continuously changing information technology landscape through the maximum utilization of innovative digital tools and methodologies.

This report Identifies the main project management components that are necessary to be considered in the successful delivery of the DigitalShift project, including all aspects of integrating the project, scope, schedule, cost, quality, resource, and risk management. The report follows the agile approach in a way that flexibility (Alsari, Qureshi & Algarni, 2020, p1(3)) and iterative development will be used in adapting to change, keeping the key deliverables in focus.

This report outlines the scope and deliverables of the project, establishes timelines and resource allocation, estimates the costs of the project, manages risks, and ensures the quality of the implementation. These are put together to ensure that TechUpGrowth will meet set objectives in smoothing internal operations (Swart et al., 2022, p85(2)), adopting a robust ERP system, introducing a customer-oriented mobile application, upgrading cybersecurity measures, and launching cloud-based operations that eventually will position it for growth.



Part 1: Project Integration Management

Task 1: Prepare a business case



Project Charter

Date



Project Title: DigitalShift – TechUpGrowth Digital Transformation Initiative

Project Start Date: 1 May 2024 Projected Finish Date: 26 August 2025

Budget Information: $10 million

Project Manager: Group Leader, xxxx-xxx-xxx, leader.group@gmail.com

Project Objectives:

  • Providing a robust ERP platform that can facilitate internal procedures.

  • Develop and publish a customer-oriented, easy-to-use mobile application to engage users.

  • Improve cybersecurity measures to safeguard the information and maintain its integrity.

  • Migrate selected operations to cloud-based solutions to unlock scalability and flexibility.

  • Provide maximum training on new technologies to people, and encourage continuous improvement.

Success Criteria:

Successful implementation of ERP with existing internal processes.

The mobile application was successfully launched and received good reviews from users with increased engagement.

Smooth transition to cloud-based solutions without operational disruption. Employee training programs, where the outcome shall be improved technology adoption rates and increased operational efficiencies.

Approach:

The project will use agile development, meaning that there will be lots of flexibility throughout its duration-18 months. Consequently, key phases of the project in order would include initiation, planning, execution, monitoring, and closure. In each phase, specific milestones and deliverables are there, and continuous contact and feedback from stakeholders will ensure progress on the project.

Roles and Responsibilities

Name and Signature

Role

Position

Contact Information

Group Leader

Project manager

Project manager


David Nguyen

IT Systems Architect

Systems Architect


James Williams

Mobile App Developer

App Developer


Michael Thompson

Cybersecurity Specialist

Cybersecurity Specialist


Lana Rey

Cloud Solutions Engineer

Cloud Solutions Specialist




Task 2: Prepare the project charter



Business Case for Project Name

Date: 1 May, 2024

Project Name: DigitalShift – TechUpGrowth Digital Transformation Initiative



  1. Introduction/ Background

TechUpGrowth is a mid-sized technology firm whose aim is to operationalize efficiency with its competitive edge by enacting a comprehensive digital transformation project. The project, named DigitalShift, looks toward the optimization of internal processes, improvement in customer experience, and integration of new emerging technologies. Anchored with $10 million, this 18-month-long engagement will witness the core update of the system, the building of new consumer-facing applications, and an enhanced cybersecurity implementation accordingly.

2.0 Business Objective

• Enhanced operational efficiency through the integration of internal processes under the ERP system.

• Develop an easy-to-use mobile application to enhance the interaction with customers.

• Enhanced cybersecurity for improved security of data.

• Migrate operations to cloud-based services for scalability and flexibility.

• Train employees on new technologies to ensure that the culture of innovation and continuous learning keeps pace.

3.0 Current Situation and Problem/Opportunity Statement

TechUpGrowth does not have updated internal systems that could impact efficiency and scalability. Buckley Firm currently has no holistic form of a digital platform on which to engage with its customers. Besides, the now cybersecurity system is shallow to protect against emerging threats from cyberspace. This opportunity is found in updating its operations and adopting innovative technologies that will enable the firm to keep pace with competitors and be efficient enough to enhance business performance.

4.0 Critical Assumption and Constraints

The project will be completed within the approved estimate of $10 million.

18 months is assumed to be enough to complete the timeline.

Dependencies will be on time, including vendor supply of cloud solutions.

Resistance to the change by employees may be a problem but must be minimized by effective strategies for managing the change.

5.0 Analysis of Options and Recommendation

  • Maintain Status Quo: just maintain the status quo, and continue with existing systems and processes. This will probably be very inefficient and carry no competitive advantage whatsoever.

  • Partial Digital Transformation: Offer select upgrades that include ERP system upgrades or mobile applications. This option addresses a few inefficiencies, though it is by no means a catch-all solution

  • Full Digital Transformation Recommended: Complete digital transformation covering ERP integration, development of their mobile app, security enhancement in cybersecurity, and migration to the cloud. This would give them maximum value in the long term it shall cover all the key use areas.


  1. Preliminary Project Requirements


  • Implementation and integration of an ERP system with the prevailing system.

  • Development of a facing customer mobile application.

  • Cybersecurity Infrastructure Development.

  • Migration of selected operations to the cloud.

  • Training employees on new systems and technologies.


7.0 Budget Estimate and Financial Analysis

A rough estimate of the budget for this DigitalShift project is around US$10 million, considering a wide area that includes the costs of technology implementation, system development, cloud services, employee training, and contingency funds in case some unforeseen risks crop up.

8.0 Schedule Estimate

The Project will take 18 months from 1st May 2024 to 26th August 2025. Projects will be worked on using agile methodologies in which deliverables are iteratively completed in Sprints.

9.0 Potential Risks

  • Delays in building full integration between the ERP system and existing technologies.

  • Employees resist changes.

  • Cybersecurity Threats during cloud migration.

  • Cost overruns due to unforeseen technical difficulties.

10.0 Exhibits

Exhibit A: Financial Analysis

A detailed cost-benefit analysis can be performed based on projected operational improvement and customer engagement.



Part 2: Project Scope Management

Task 3: Develop an initial scope management



Scope Statement (Version xx)



Project Title: DigitalShift – TechUpGrowth Digital Transformation Initiative


Date: 1 May 2024 Prepared by: Group leader

Project Justification:

TechUpGrowth sees the DigitalShift project as so critical in bringing it closer to renewing its operations, increasing customer interaction, and standing it in better stead against a constantly changing technology environment. The result will be greater integration of cutting-edge digital technologies, smoothing of internal procedures, and overall operational efficiency through ERP implementation, mobile app development, cloud migration, and cybersecurity enhancements.

Product Characteristics and Requirements:

  1. System integration/implementation of ERP to automate as well as optimize all business processes.

  2. Development of a mobile application to increase interaction and engagement with customers.

  3. Migration of selected internal operations and processes to cloud-based infrastructure.

  4. Advanced cybersecurity measures need to be implemented to protect the data and ensure the continuity of business.

Product User Acceptance Criteria:

  • The ERP should be integrated into the existing systems and show quantifiable enhancement of operational efficiency within three months of implementation.

  • Get an average user satisfaction rating of at least 85% for the mobile application, within the first three months of operation.

  • Cloud infrastructure: Cloud infrastructure should scale effortlessly with less than 2% or less downtime during and after the migration.

  • Improvements in cybersecurity shall demonstrate a reduction in vulnerabilities, such that the mean security level for the executed system should be raised. This shall be verified through a third-party safety audit.

Summary of Project Deliverables

  • Project management-related deliverables:

Business case, project charter, team contract, scope statement, work breakdown structure (WBS), project schedule, cost baseline, status reports, final project presentation, final project report, lessons learned report, risk register, and other documentation as may be required to support good project management

  • Product-related deliverables:

Research reports, design documents, ERP systems, mobile applications, infrastructure based on the cloud, cybersecurity framework, employee training materials, and documentation about system implementation and testing.

1. ERP System and Integration Report.

2. Creating, developing, and publishing mobile apps.

3. Cloud migration and scalability infrastructure.

4. Improvement of cybersecurity and the vulnerability assessment.





Task 4: Develop a work breakdown structure (WBS)


Work Breakdown Structure (WBS)

Date



Project Name: DigitalShift – TechUpGrowth Digital Transformation Initiative



1.0 Project Initiation

1.1 Project Management

1.1.1 Develop project charter

1.1.2 Assemble project team

1.1.3 Define project objectives

1.1.4 Initial stakeholder meetings



1.2 Documentation and Planning

1.2.1 Prepare business case

1.2.2 Create project management plans

1.2.3 Define scope management plan

1.2.4 Create a risk management plan



2.0 ERP System Implementation

2.1 Planning and Requirements Gathering

2.1.1 Conduct needs assessment

2.1.2 Identify key business processes for ERP integration

2.1.3 Define ERP system specifications



2.2 ERP Development and Integration

2.2.1 Design ERP system architecture

2.2.2 Customize ERP modules to align with business requirements

2.2.3 Integrate ERP with existing internal systems

2.2.4 Conduct system testing and validation



2.3 ERP Rollout and Training

2.3.1 Roll out ERP system

2.3.2 Provide user training for employees

2.3.3 Monitor ERP system performance



3.0 Mobile Application Development

3.1 Requirements and Design

3.1.1 Identify user needs and requirements

3.1.2 Develop mobile app wireframes and prototypes

3.1.3 Define key features and functionality



3.2 App Development and Testing

3.2.1 Code app functionality

3.2.2 Perform app testing (beta release)

3.2.3 Address bugs and user feedback



3.3 Launch and User Engagement

3.3.1 Official app launch

3.3.2 Monitor user feedback and satisfaction

3.3.3 Conduct post-launch improvements



4.0 Cloud Infrastructure Migration

4.1 Planning and Requirements

4.1.1 Evaluate current systems for cloud compatibility

4.1.2 Define cloud infrastructure requirements

4.1.3 Select cloud service provider



4.2 Migration Execution

4.2.1 Prepare systems for migration

4.2.2 Conduct phased cloud migration

4.2.3 Test and validate cloud operations



4.3 Post-Migration Support

4.3.1 Monitor cloud system performance

4.3.2 Optimize Cloud Services

4.3.3 Provide cloud infrastructure training

5.0 Cybersecurity Enhancements

5.1 Assessment and Planning

5.1.1 Conduct security gap analysis

5.1.2 Define cybersecurity requirements and protocols

5.1.3 Identify key vulnerabilities



5.2 Security Implementation

5.2.1 Implement security solutions (firewalls, encryption, etc.)

5.2.2 Integrate security with cloud and ERP systems

5.2.3 Conduct security testing



5.3 Monitoring and Training

5.3.1 Continuous security monitoring

5.3.2 Train employees on security best practices

5.3.3 Update security protocols as needed

WBS Dictionary Entry

Date



Project Name: DigitalShift – TechUpGrowth Digital Transformation Initiative

WBS Item Number: 2.2

WBS Item Name: ERP Development and Integration

Description: The work will involve designing an ERP system and customizing it to integrate and test for the internal business (Tarigan et al, 2021, p283(1)) processes of TechUpGrowth. This will drive key workflow automation, to attain operational efficiency, fuller visibility of information, and more file-private decision-making with less wastage of time. Architecture design, system customization, module integration, and thorough testing characterize this phase to ensure the ERP system meets all operational and performance requirements. This service will also involve the smooth integration of the ERP system with other existing technologies to prevent disruptions of business.



Part 3: Project Schedule Management

Task 5: Gantt chart for WBS

Team Project Draft Schedule

 

 

 

Total hours->

176

157

181

149

173

836

154

138

175

131

171

769

Major tasks

Start Date

End Date

Responsible

Estimated Hours per person

Total

Actual Hours

Total

 

 

 

 

A

B

C

D

E

Est. Hours

A

B

C

D

E

Act. Hours

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Start Date

End Date

Michael

10

10

10

10

15

 

10

5

10

8

15

 

1.0 Project Initiation

1st May 2024

30th June 2024

David

3

5

4

5

5

 

3

5

4

5

10

 

1.1 Project Management

1st May 2024

30th June 2024

Lana

2

3

4

5

5

 

5

0

6

5

3

 

1.1.1 Develop project charter

1st May 2024

15th May 2024

Team

2

2

2

2

5

 

3

3

3

5

3

 

1.1.2 Assemble project team

16th May 2024

31st May 2024

 

 

 

 

 

 

 

 

 

 

 

 

 

1.1.3 Define project objectives

1st June 2024

15th June 2024

 

3

5

4

4

10

 

5

5

6

2

10

 

1.1.4 Initial stakeholder meetings

16th June 2024

30th June 2024

 

4

5

10

5

10

 

5

4

5

5

10

 

1.2 Documentation and Planning

1st May 2024

30th June 2024

 

5

5

6

5

3

 

5

0

0

6

5

 

1.2.1 Prepare business case

1st May 2024

15th May 2024

 

 

 

 

 

 

 

 

 

 

 

 

 

1.2.2 Create project management plans

16th May 2024

15th June 2024

Michael

5

5

6

10

8

 

5

5

6

10

8

 

1.2.3 Define scope management plan

16th June 2024

30th June 2024

David

5

4

5

5

10

 

0

5

5

0

10

 

1.2.4 Create a risk management plan

16th June 2024

30th June 2024

Lana

4

4

5

6

4

 

0

4

5

4

0

 

2.0 ERP System Implementation

1st July 2024

30th April 2025

David

4

5

4

8

8

 

0

4

0

8

8

 

2.1 Planning and Requirements Gathering

1st July 2024

31st October 2024

 

15

10

10

10

15

 

15

15

15

0

15

 

2.1.1 Conduct needs assessment

1st July 2024

31st July 2024

 

 

 

 

 

 

 

 

 

 

 

 

 

2.1.2 Identify key business processes for ERP

1st August 2024

30th September 2024

 

 

 

 

 

 

 

 

 

 

 

 

 

2.1.3 Define ERP system specifications

1st October 2024

31st October 2024

David

5

5

6

0

0

 

5

5

6

0

0

 

2.2 ERP Development and Integration

1st November 2024

30th April 2025

David

8

8

10

5

7

 

0

8

10

5

7

 

2.2.1 Design ERP system architecture

1st November 2024

30th November 2024

 

10

10

10

0

0

 

10

10

10

0

0

 

2.2.2 Customize ERP modules

1st December 2024

31st January 2025

 

10

10

10

10

10

 

12

12

12

12

12

 

2.2.3 Integrate ERP with internal systems

1st February 2025

31st March 2025

James

5

5

5

10

0

 

5

5

5

10

0

 

2.2.4 System testing and validation

1st April 2025

30th April 2025

 

 

 

 

 

 

 

 

 

 

 

 

 

2.3 ERP Rollout and Training

1st May 2025

31st July 2025

Michael

4

4

5

0

0

 

4

4

5

0

0

 

2.3.1 Roll out ERP system

1st May 2025

31st May 2025

Lana

10

10

10

10

10

 

10

0

10

10

10

 

2.3.2 Provide user training

1st June 2025

30th June 2025

Michael

10

0

12

0

8

 

10

0

12

0

8

 

2.3.3 Monitor ERP system performance

1st July 2025

31st July 2025

 

5

5

5

5

5

 

5

5

0

5

0

 

3.0 Mobile Application Development

1st August 2025

30th November 2025

Jackson

5

5

4

5

5

 

5

5

4

5

5

 

3.1 Requirements and Design

1st August 2025

30th September 2025

 

 

 

 

 

 

 

 

 

 

 

 

 

3.1.1 Identify user needs and requirements

1st August 2025

15th August 2025

Team

3

3

0

5

0

 

3

3

0

5

0

 

3.1.2 Develop mobile app wireframes and prototypes

16th August 2025

15th September 2025

Jackson

4

4

4

4

10

 

4

4

4

4

10

 

3.1.3 Define key features and functionality

16th September 2025

30th September 2025

 

10

10

10

10

10

 

0

12

12

12

12

 

3.2 App Development and Testing

1st October 2025

15th November 2025

Michael

5

5

5

5

5

 

5

5

5

5

5

 

3.2.1 Code app functionality

1st October 2025

15th October 2025

 

 

 

 

 

 

 

 

 

 

 

 

 

3.2.2 Perform app testing (beta release)

16th October 2025

31st October 2025

Lana

5

5

0

0

0

 

5

5

0

0

0

 

3.2.3 Address bugs and user feedback

1st November 2025

15th November 2025

James

5

5

5

5

5

 

5

0

5

0

5

 

3.3 Launch and User Engagement

16th November 2025

30th November 2025

Lana

10

0

10

0

0

 

10

0

10

0

0

 

3.3.1 Official app launch

16th November 2025

20th November 2025

James

5

10

0

0

5

 

10

5

5

0

0

 

3.3.2 Monitor user feedback and satisfaction

21st November 2025

30th November 2025

David

10

5

5

5

0

 

10

5

0

5

5

 



Figure 1:Gantt Chart

Figure 2: Gantt Chart

Milestone

  1. Completion of Project Charter (PR1): Project Charter Completion marks the final resolution or determination of the base for project goals and objectives (Kamali, 2020, p53(3)).

  2. Kick-off Meeting PR1: The kick-off meeting, when well conducted, aligns the team members and stakeholders in terms of project expectations.

  3. Draft Scope Statement Approval PR1: An approval of the draft scope statement confirms project boundaries and deliverables.

  4. Completion of Gantt Chart (PR2): Finalization of the Gantt chart will provide a clear, pictorial timeline for the project tasks and their scheduling.

  5. Final Presentation Complete: The task represents the final presentation of the project complete and stakeholders signing off.

Part 4: Project Cost and Quality Management

Task 6: Documents for cost estimate

Cost Estimate

Project Name: DigitalShift – TechUpGrowth Digital Transformation Initiative


Date:

 

 

 

 

 

 

 

 

Labour

Internal

$/hour

Internal

External

$/hour

External

Total

Non-labor $

Total Cost

WBS Categories

Hours

Labor

 

$ Total

Labor

 

$ Total

Labor

 

 

1.0 Project Initiation

1.1 Project Management

100

50

$100

$5,000

20

$120

$2,400

$7,400

$1,000

$8,400

1.2 Documentation and Planning

150

75

$100

$7,500

30

$120

$3,600

$11,100

$2,000

$13,100

2.0 ERP System Implementation

2.1 Planning and Requirements Gathering

200

100

$120

$12,000

50

$150

$7,500

$19,500

$5,000

$24,500

2.2 ERP Development and Integration

800

400

$150

$60,000

200

$200

$40,000

$100,000

$20,000

$120,000

2.3 ERP Rollout and Training

300

150

$120

$18,000

80

$150

$12,000

$30,000

$10,000

$40,000

3.0 Mobile Application Development

3.1 Requirements and Design

100

50

$100

$5,000

20

$120

$2,400

$7,400

$1,000

$8,400

3.2 App Development and Testing

400

200

$120

$24,000

100

$150

$15,000

$39,000

$8,000

$47,000

3.3 Launch and User Engagement

100

50

$100

$5,000

20

$120

$2,400

$7,400

$1,000

$8,400

4.0 Cloud Infrastructure Migration

4.1 Planning and Requirements

100

50

$100

$5,000

20

$120

$2,400

$7,400

$1,000

$8,400

4.1 Planning and Requirements

100

50

$100

$5,000

20

$120

$2,400

$7,400

$1,000

$8,400

4.2 Migration Execution

300

150

$120

$18,000

80

$150

$12,000

$30,000

$8,000

$38,000

4.3 Post-Migration Support

100

50

$100

$5,000

20

$120

$2,400

$7,400

$1,000

$8,400

5.0 Cybersecurity Enhancements

5.1 Assessment and Planning

100

50

$100

$5,000

20

$120

$2,400

$7,400

$1,000

$8,400

5.2 Security Implementation

300

150

$120

$18,000

80

$150

$12,000

$30,000

$8,000

$38,000

5.3 Monitoring and Training

100

50

$100

$5,000

20

$120

$2,400

$7,400

$1,000

$8,400

Subtotal

 

 

 

$305,100

 

 

$105,600

$410,700

$100,000

$510,700

Reserves

 

 

 

 

 

 

 

 

 

$20,000

Total

 

 

 

 

 

 

 

 

 

$1,00,00,000




Cost Estimate

Project Name: Digital Shift

Date:

 

 

 

 

 

 

 

 

 

 

 

 

Month

 

1

2

3

4

5

6

7

8

9

10

11

12

Total Cost

WBS Categories

 

 

 

 

 

 

 

 

 

 

 

 

 

1. Project Initiation

 

1.1 Project Management













 

1.1.1 Develop project charter

20000












20,000

1.1.2 Assemble project team

10000

20000











30,000

1.1.3 Define project objectives

10000

10000











20,000

1.1.4 Initial stakeholder meetings

10000

10000

10000










30,000

1.2 Documentation and Planning













 

1.2.1 Prepare business case

20000

10000

10000

10000









50,000

1.2.2 Create project management plans


20000

20000

10000









50,000

1.2.3 Define scope management plan



20000

30000









50,000

1.2.4 Create a risk management plan




50000









50,000

2.0 ERP System Implementation

 

2.1 Planning and Requirements Gathering













 

2.1.1 Conduct needs assessment



50000

50000









1,00,000

2.1.2 Identify key business processes for ERP integration



20000

50000

50000

50000







2,00,000

2.1.3 Define ERP system specifications



30000

50000

100000

50000







2,00,000

2.2 ERP Development and Integration













 

2.2.1 Design ERP system architecture




100000


100000

100000






3,00,000

2.2.2 Customize ERP modules to align with business requirements




100000

100000


100000

200000





5,00,000

2.2.3 Integrate ERP with existing internal systems




50000

50000

50000

100000

50000





3,00,000

2.2.4 Conduct system testing and validation




50000

100000

50000

100000

100000





4,00,000

2.3 ERP Rollout and Training













 

2.3.1 Roll out ERP system






50000

50000

50000

50000




2,00,000

2.3.2 Provide user training for employees





50000

50000

50000

50000





2,00,000

2.3.3 Monitor ERP system performance









50000

50000



1,00,000

3.0 Mobile Application Development

 

3.1 Requirements and Design







50000

100000

50000

100000



3,00,000

3.1.1 Identify user needs and requirements







20000

30000

40000

10000



1,00,000

3.1.2 Develop mobile app wireframes and prototypes







10000

30000

20000

40000



1,00,000

3.1.3 Define key features and functionality





10000

10000

10000

30000

10000

30000



1,00,000

3.2 App Development and Testing













 

3.2.1 Code app functionality






100000

100000

100000

100000

100000



5,00,000

3.2.2 Perform app testing (beta release)





50000

50000

50000

50000

50000

50000



3,00,000

3.2.3 Address bugs and user feedback






20000

30000

100000

30000

20000



2,00,000

3.3 Launch and User Engagement













 

3.3.1 Official app launch







50000

50000

50000

50000



2,00,000

3.3.2 Monitor user feedback and satisfaction





50000

50000

50000

50000





2,00,000

3.3.3 Conduct post-launch improvements






20000

20000

20000

20000

20000



1,00,000

4.0 Cloud Infrastructure Migration

 

4.1 Planning and Requirements













 

4.1.1 Evaluate current systems for cloud compatibility









200000

100000



3,00,000

4.1.2 Define cloud infrastructure requirements








200000

100000




3,00,000

4.1.3 Select cloud service provider







100000

100000

100000

100000



4,00,000

4.2 Migration Execution













 

4.2.1 Prepare systems for migration







40000

40000

40000

40000

40000


2,00,000

4.2.2 Conduct phased cloud migration






40000

40000

40000

40000

40000



2,00,000

4.2.3 Test and validate cloud operations





20000

20000

20000

20000

20000




1,00,000

4.3 Post-Migration Support













 

4.3.1 Monitor cloud system performance







10000

10000

10000

10000

10000


50,000

4.3.2 Optimize Cloud Services








10000

10000

10000

10000

10000

50,000

4.3.3 Provide cloud infrastructure training










30000

50000

20000

1,00,000

5.0 Cybersecurity Enhancements









100000

300000

200000

300000

9,00,000

Subtotal

70000

70000

160000

550000

580000

710000

1100000

1430000

1090000

1100000

310000

330000

7500000

Reserves













2500000

Total













1,00,00,000

Task 6: Business case financial analysis

Financial Analysis for DigitalShift




Created by:

 

Date:

 

 

 




Discount rate

8%

 

 

 

 

 




 

 

 

 

 

 

 


Years

Cumulative benefits - costs

Assume the project is completed in Year 0

 

 

Year

 

 

 


0

-10000000

 

0

1

2

3

Total

 


1

7,40,741

Costs

1,00,00,000

0

0

0

 

 


2

9314129

Discount factor

1.00

0.93

0.86

0.79

 

 


3

13283290

Discounted costs

1,00,00,000

-

-

-

1,00,00,000

 




 

 

 

 

 

 

 




Benefits

0

10000000

10000000

5000000

 

 




Discount factor

1.00

0.93

0.86

0.79

 

 




Discounted benefits

0

9259259

8573388

3969161

2,18,01,809

 




 

 

 

 

 

 

 




Discounted benefits - costs

(1,00,00,000)

92,59,259

85,73,388

39,69,161

Shape1

1,18,01,809


NPV




Cumulative benefits - costs

(1,00,00,000)

7,40,741

Shape2

93,14,129


1,32,83,290

 

 




Shape3

 


 

 

 

 

 

 




ROI

118%

 

 

 

 

 




 

Payback in Year X

1.4 Years

 

 




Assumptions

 

 

 

 

 

 







Part 5: Project Resource Management

Task 7: Responsibility Assignment Matrix (RACI Chart) for the WBS

RACI MATRIX

PROJECT DETAILS






 

 






PROJECT No:

MA-015-02






DATE:

 






FULL PROJECT NAME:

Project Digital Shift






PROJECT MANAGER:

Group Leader






RACI

Task

Project Manager

IT Systems Architect

Mobile App Developer

Cybersecurity Specialist

Cloud Solutions Engineer

Change Management Consultant

1.0 Project Initiation

 

 

 

 

 

 

1.1 Project Management

A

R

 

 

 

C

1.1.1 Develop project charter

A

R

 

 

 

C

1.1.2 Assemble project team

A

 

 

 

 

R

1.1.3 Define project objectives

A

R

 

 

 

C

1.1.4 Initial stakeholder meetings

A

R

 

 

 

C

1.2 Documentation and Planning

 

 

 

 

 

 

1.2.1 Prepare business case

A

R

 

 

 

C

1.2.2 Create project management plans

A

R

 

 

 

C

1.2.3 Define scope management plan

A

R

 

 

 

C

1.2.4 Create risk management plan

A

R

 

 

 

C

2.0 ERP System Implementation

 

 

 

 

 

 

2.1 Planning and Requirements Gathering

 

 

 

 

 

C

2.1.1 Conduct needs assessment

A

R

 

 

 

C

2.1.2 Identify key business processes for ERP integration

A

R

 

 

 

C

2.1.3 Define ERP system specifications

A

R

 

 

 

C

2.2 ERP Development and Integration

 

 

 

 

 

 

2.2.1 Design ERP system architecture

 

A

 

 

 

R

2.2.2 Customize ERP modules to align with business requirements

A

C

 

 

 

R

2.2.3 Integrate ERP with existing internal systems

A

R

 

 

C

 

2.2.4 Conduct system testing and validation

 

R

C

 

 

 

2.3 ERP Rollout and Training

 

 

 

 

 

 

2.3.1 Roll out ERP system

A

R

 

 

 

C

2.3.2 Provide user training for employees

A

 

 

 

 

C

2.3.3 Monitor ERP system performance

A

 

 

 

R

 

3.0 Mobile Application Development

 

 

 

 

 

 

3.1 Requirements and Design

 

 

 

 

 

 

3.1.1 Identify user needs and requirements

A

 

R

 

 

C

3.1.2 Develop mobile app wireframes and prototypes

 

 

A

 

 

C

3.1.3 Define key features and functionality

A

 

R

 

 

C

3.2 App Development and Testing

 

 

 

 

 

 

3.2.1 Code app functionality

 

 

A

 

 

C

3.2.2 Perform app testing (beta release)

A

 

R

 

 

C

3.2.3 Address bugs and user feedback

A

 

R

 

 

C

3.3 Launch and User Engagement

 

 

 

 

 

 

3.3.1 Official app launch

A

 

R

 

 

C

3.3.2 Monitor user feedback and satisfaction

A

 

 

 

 

C

3.3.3 Conduct post-launch improvements

A

 

 

 

 

C

4.0 Cloud Infrastructure Migration

 

 

 

 

 

 

4.1 Planning and Requirements

 

 

 

 

 

 

4.1.1 Evaluate current systems for cloud compatibility

A

R

 

 

 

C

4.1.2 Define cloud infrastructure requirements

A

R

 

 

 

C

4.1.3 Select cloud service provider

A

 

 

 

R

C

4.2 Migration Execution

 

 

 

 

 

 

4.2.1 Prepare systems for migration

A

 

 

 

R

C

4.2.2 Conduct phased cloud migration

A

 

 

 

R

C

4.2.3 Test and validate cloud operations

A

R

 

 

 

C

4.3 Post-Migration Support

 

 

 

 

 

 

4.3.1 Monitor cloud system performance

A

 

 

 

R

C

4.3.2 Optimize cloud services

A

 

 

 

R

C

4.3.3 Provide cloud infrastructure training

A

 

 

 

R

C

5.0 Cybersecurity Enhancements

 

 

 

 

 

 

5.1 Assessment and Planning

 

 

 

 

 

 

5.1.1 Conduct security gap analysis

A

 

 

R

 

C

5.1.2 Define cybersecurity requirements and protocols

A

 

 

R

 

C

5.1.3 Identify key vulnerabilities

A

 

 

R

 

C

5.2 Security Implementation

 

 

 

 

 

 

5.2.1 Implement security solutions (firewalls, encryption, etc.)

A

 

 

R

 

C

5.2.2 Integrate security with cloud and ERP systems

A

 

 

R

 

C

5.2.3 Conduct security testing

A

 

 

R

 

C

5.3 Monitoring and Training

 

 

 

 

 

 

5.3.1 Continuous security monitoring

A

 

 

R

 

C

5.3.2 Train employees on security best practices

A

 

 

R

 

C

5.3.3 Update security protocols as needed

A

 

 

R

 

C





Part 6: Project Risk Management

Task 8: Create a risk register

Table 1 Risk register


Risk Register for DigitalShift

Date

Project Name:

DigitalShift – TechUpGrowth Digital Transformation Initiative


















cc

Rank

Risk

Description

Category

Root Cause

Triggers

Potential Responses

Risk Owner

Probability

Impact

Status

1

High

Schedule Delays

Key milestones are missed, affecting overall timelines.

Schedule Risk

Underestimation of task durations

Resource unavailability, unexpected issues

Reassess timelines and allocate additional resources

Project Manager

70%

High

Open

2

Medium

Budget Overruns

Project costs exceed budgeted amounts.

Financial Risk

Scope creep, inaccurate estimates

Change requests, price increases

Tighten budget controls and monitor expenses closely

Finance Manager

50%

Medium

Open

3

High

Technology Failure

Critical software/hardware fails during project execution.

Technical Risk

Lack of testing or support

System errors, compatibility issues

Ensure thorough testing and have backup systems in place

IT Manager

60%

High

Open

4

Low

Stakeholder Resistance

Key stakeholders are not supportive of project changes.

Stakeholder Risk

Poor communication

Negative feedback, lack of engagement

Engage stakeholders regularly and communicate benefits

Project Sponsor

40%

Low

Open

5

Medium

Resource Availability

Necessary resources (human or material) are unavailable.

Resource Risk

Competition for resources

Staff turnover, other project commitments

Create a resource management plan and schedule flexibility

HR Manager

50%

Medium

Open

6

High

Regulatory Changes

New regulations affect project compliance and requirements.

Compliance Risk

Policy changes

Government announcements, industry trends

Monitor regulatory environment and adjust plans as needed

Compliance Officer

70%

High

Open

7

Medium

Communication Breakdown

Poor communication leads to misunderstandings and errors.

Communication Risk

Lack of a clear communication plan

Team member turnover, cultural differences

Establish regular meetings and clear communication channels

Project Manager

60%

Medium

Open

8

Low

Market Changes

Changes in the market affect project viability.

Market Risk

Economic downturn, competitor actions

Market reports, competitor news

Conduct market analysis and adjust project scope if needed

Market Analyst

30%

Low

Open

9

High

Data Security Breach

Unauthorized access to project data occurs.

Security Risk

Weak security measures

Phishing attacks, insider threats

Implement strict security protocols and regular audits

IT Security Lead

80%

High

Open

10

Medium

Skills Shortage

Team lacks necessary skills for project completion.

Resource Risk

Inadequate training

Skills assessment results, project requirements

Provide training or hire specialized resources

HR Manager

50%

Medium

Open



Task 9: Plot the risks on a Probability/Impact Matrix



Figure 3 Risk matrix



Summary

DigitalShift – TechUpGrowth Digital Transformation Initiative: This is an implementation project for ERP, mobile application development, cloud infrastructure migration, and strengthening cybersecurity. The activities and deliverables to be made are detailed in the Work Breakdown Structure. To manage and accomplish the project, the comprehensive structure and schedule have been worked out: The Risk Register includes the name of the risk, description, cause, effect, mitigation, responsibility, and date of resolution, accompanying the risk assessment in the Probability/Impact Matrix, delays in the schedule, exceeding the budget, and data security breaches. This involves the prioritization of high-effect risks and the development of strategies to mitigate those risks to ensure that the project will be completed within the scheduled timeline and the approved budget, ultimate success in operations, and customer/stakeholder satisfaction.



References

  1. Alsari, A., Qureshi, R. & Algarni, A. 2020, October. Agile framework to transform traditional team, In 2020 IEEE Frontiers in Education Conference (FIE), pp. 1-9). IEEE. https://www.researchgate.net/profile/M-Rizwan-Qureshi/publication/346082624_Agile_Framework_To_Transform_Traditional_Team/links/5fba89d5a6fdcc6cc65c6869/Agile-Framework-To-Transform-Traditional-Team.pdf

  2. Kamali, A. 2020. Applying PMBOK in Project-Based ERP Logistics Systems. CiiT International Journal of Programmable Device Circuits And Systems, 12(3), pp.51-61. https://www.academia.edu/download/64066910/Applying%20PMBOK%20in%20Project%20Based%20ERP%20Logistics%20Systems.pdf

  3. Swart, K., Bond-Barnard, T. & Chugh, R., 2022. Challenges and critical success factors of digital communication, collaboration and knowledge sharing in project management virtual teams: a review. International Journal of Information Systems and Project Management10(4), pp.84-103. https://acquire.cqu.edu.au/articles/journal_contribution/Challenges_and_critical_success_factors_of_digital_communication_collaboration_and_knowledge_sharing_in_project_management_virtual_teams_a_review/25183502/1/files/44462810.pdf

  4. Tarigan, Z.J.H., Suprapto, W., Harjanti, D., Malelak, M.I. & Basana, S.R. 2021. Key user ERP capability maintaining ERP sustainability through effective design of business process and integration data management Key user ERP capability maintaining ERP sustainability through effective design of business process and integration data management, (Doctoral dissertation, Petra Christian University). https://repository.petra.ac.id/19170/10/3_Key_user_ERP_capability_maintaining_ERP_sustainability_through_effective_design_of_business.pdf



Appendices

Meeting Agenda

Meeting/Project Name:

DigitalShift – TechUpGrowth Digital Transformation Initiative

Date of Meeting: (MM/DD/YYYY)

29 March 2024

Time:

11:00 AM

Meeting Facilitator:

Team leader

Location:

Conference Room



1. Meeting Objective

Discussion on the status of the Digital Transformation Initiative, review of the risk register, and set up next steps in the project.



2. Attendees

Name

Department/Division

E-mail

Phone

Team Leader

Project Management



David Nguyen

IT Department



James Williams

Finance



Lana Rey

Operations



Michael Thompson

Cybersecurity





3. Meeting Agenda

Topic

Owner

Time

Project progress updates

Team Leader

30 mins

Review of the risk register

Team Leader

20 mins

Discussion of next steps and action items

Team Leader

20 mins

Open floor for questions and feedback

All team members

30 mins



4. Pre-work/Preparation (documents/handouts to bring, reading material, etc.)

Description

Prepared by

Current project progress report

Team Leader

Updated risk register

David Nguyen

Action item list from the previous meeting

Lana Rey



Meeting Minute



Meeting/Project Name:

DigitalShift – TechUpGrowth Digital Transformation Initiative


Date of Meeting: (MM/DD/YYYY)

29 March 2024

Time:

11:00 AM


Minutes Prepared By:

Team Leader

Location:

Conference Room


1. Meeting Objective


Discussion on the status of the Digital Transformation Initiative, review of the risk register, and setup next steps in the project.



2. Attendance at Meeting


Name

Department/Division

E-mail

Phone


Team Leader

Project Management




David Nguyen

IT Department




James Williams

Finance




Lana Rey

Operations




Michael Thompson

Cybersecurity




3. Agenda and Notes, Decisions, Issues


Topic

Owner

Time




Project progress updates


Team Leader

30 min




Review of the risk register


David Nguyen

20 min


Discussion of next steps and action items




Lana Rey

30 min


Open floor for questions and feedback

All team members

20 min


4. Action Items


Action

Owner

Due Date


Update project progress report

Team Leader

1/005/2024


Finalize risk mitigation strategies

David Nguyen

05/05/2024


Prepare training materials for ERP system

Lana Rey

15/05/2024


Schedule follow-up meeting

Team Leader

1/06/2024


5. Next Meeting (if applicable)


Date: (MM/DD/YYYY)

6/05/2024

Time:

12:00 AM

Location:

Conference Room


Objective:

Overview Follow the updated progress of the project to finalize risk management strategies.





43