DigitalShift: A Strategic Project for TechUpGrowth's Operational Infrastructure Renewal

Faculty of Higher Education

Group Assignment Cover Sheet

This cover sheet must be submitted with your assignment

Unit

Details

Unit Name

IS Project Management

Code

HI5029

Year

2024

Trimester number



Assessment

Details

Assessment Name


Due Date: dd/mm/yyyy



Group Number





** only list students who have contributed to this assignment

Group

Details

Student ID

First Name

Family Name

Contribution %



















Group

Submission

Declaration

Integrity Declaration

We have read and understand academic integrity policies and practices and our assessment does not violate these.


Student ID

First Name

Family Name









Submission Date


Executive Summary

DigitalShift is a pan-company-wide initiative undertaken by the mid-sized technology company called TechUpGrowth, aimed at wholly transiting the operational infrastructure to one that is not only more efficient but also more customer-engaging. As such, it set a budget of US$10 million and a timeline of 18 months for focused implementation of a robust ERP solution, development of a customer-focused mobile app, cybersecurity upgrade, and migration to cloud-based solutions. The project also aims at value addition in terms of internal process flow towards more smoothness, ensuring data security, and bringing a culture of continuous improvement amongst the employees. Operational challenges in present and presenting TechUpGrowth for further growth in a competitive market all might be possible through the agile approach the project management has adopted. It promises to yield a 44% Return on Investment within three years and hence holds great importance for ensuring the sustainability and adaptability of the company considering the times of technology change.









Introduction

DigitalShift is one of the strategic projects TechUpGrowth has taken up in pursuit of renewal for operational infrastructure and maintaining competitiveness in the fast-evolving technology industry. This also involves Enterprise Resource Planning integration, updating cybersecurity, creating a customer-oriented mobile app, and migrating to the cloud. This project will help in smoothing out the inner processes, strengthening data security, and engaging customers, thereby assuring the maintenance of operational efficiency and scalability (Khodurska, M. 2020, p.87(1)). DigitalShift has ensured that with an 18-month timeline and a budget presupposed at $10 million, TechUpGrowth is well set to meet new challenges and opportunities.

Objectives

  • Provide an ERP system that would facilitate internal processes with ease and accessibility of data.

  • Develop a customer-oriented mobile app to enhance engagement and personalization (Soubra, 2021, p1(5)).

  • Enhance cybersecurity infrastructure to protect sensitive data and reduce risks.

  • Scale as needed, and move to the cloud for increased flexibility and efficiency.

  • Offer all-around employee training to introduce new systems and technologies smoothly.

  • Create an enabling culture of continuous improvement and innovation.

  • The operational efficiency and improved customer satisfaction, a return on investment of at least 44% within three years.



Part 1: Project Integration Management

Task 1: Prepare a business case

Business Case for Project Name

Date

Project Name: Digital Shift – TechUpGrowth

  1. Introduction/ Background

TechUpGrowth comes within the ambit of medium-sized technology entities. The aim here is to usher in digitization on all fronts and make it competitive at the scorching pace of the technological world by improvements in internal processes, enriching customer experience, and leveraging emerging technologies. To this effect, a project called DigitalShift has been proposed, dedicated to these ends, scheduled for a timeline of 18 months with an estimated $10 million cost.

2.0 Business Objective

The focus of the DigitalShift project is operational efficiency, enhanced customer experience, and the use of new technologies that ensure scalability, flexibility, and security. Among the major activities of this project are enhancing internal company systems with an ERP system, developing a mobile application for customers to improve interaction, and implementing of robust cybersecurity along with cloud-based solutions.

3.0 Current Situation and Problem/Opportunity Statement

TechUpGrowth has been facing challenges in operational efficiency, data security, and effective customer engagement. Its current infrastructure is old and incapable of functioning with quite many modern technologies. This project provides an opportunity for the streamlining of operations, and induction of technologies that are oriented towards customers, making the systems of the company capable of supporting future growth.

4.0 Critical Assumptions and Constraints

  • Assumption: All departments will not object to the implementation of new technologies.

  • Constraint: Limited resources for training and avoidance from employees themselves.

  • Assumption: The solutions will inherently be compatible with existing infrastructure hosted in the cloud.

  • Constraint: Minimizing disruption to normal operational running while the change is being affected.

5.0 Analysis of Options and Recommendation

Two variants of options have been studied:

1. Option 1: Partial transformation by upgrading the critical systems only.

2. Option 2: Full-scale digital transformation as proposed in DigitalShift. Recommendation: The full-scale transformation option, Option 2, is recommended to make things more efficient and competitive in the long run.

6.0 Preliminary Project Requirements

It involves the implementation of ERP, the creation of a mobile application, migration to the cloud, and reinforcement in cybersecurity. The personnel will surely require training on all the new technologies put at their disposal.

7.0 Budget Estimate and Financial Analysis

The total budget for DigitalShift is US$10 million, including software licensing, implementation costs training, and infrastructure upgrades. Financial analysis estimates the project to realize a positive return on investment in three years by enhancing operational efficiency and customer satisfaction.

8.0 Schedule Estimate

It will take approximately 18 months. The key milestones include the completion of ERP in month 9, a mobile application release in month 12, full system testing, and employee training by month 18.

9.0 Potential Risks

These are risks around employee resistance to change, integration with existing systems, and cybersecurity risks not forecasted, among others. The strategy to mitigate the risk will, therefore, revolve around training and the constant monitoring of the performance of the system.

10.0 Exhibits

Exhibit A: Financial Analysis



Task 2: Prepare the project charter

Project Charter

Date

Project Title: DigitalShift – TechUpGrowth

Project Start Date: 01/12/2024
Projected Finish Date: 31/05/2026

Budget Information:

This project has a $10 million budget to complete all the stages of the project.

Project Manager:

Name: John Smith Root,

phone: +61- 4XX-XXX-XXXX,

E-mail: john.smith.root@techupgrowth.com

Project Objectives:

The DigitalShift will digitize the operation of TechUpGrowth with the ERP system implementation, development and deployment of a customer-facing mobile application, migration on cloud infrastructure, and enhancement of cybersecurity.

Success Criteria:

Success will be realized if the following aspects are achieved in the project:

  • An integrated, functioning ERP system.

  • The mobile application is released, enhancing customer interaction by 20% in just six months.

  • The cyber vulnerabilities are reduced by 50%.

  • Train all employees to understand and be capable of using new systems.


Approach:

It will be managed to ensure flexibility using an agile approach to project management. This project will be executed through several phases: initiation, planning, execution, and closure. The stakeholders will always be informed of the progress, while obstacles will be resolved as soon as possible.

Roles and Responsibilities

Name and Signature

Role

Position

Contact Information

John Smith Root

Project Manager

Project Manager

john.smith.root@techupgrowth.com

David Nguyen

IT Systems Architect

Systems Architect

david.nguyen@techupgrowth.com

Michael Thompson

Cybersecurity Specialist

Cybersecurity Lead

michael.thompson@techupgrowth.com

Jane Doe

Cloud Solutions Engineer

Cloud Engineer

jane.doe@techupgrowth.com

Richard Evans

Mobile Application Developer

Software Developer

richard.evans@techupgrowth.com

Comments: N/A



Part 2: Project Scope Management

Task 3: Develop an initial scope management

Scope Statement (Version xx)

Project Title: DigitalShift – TechUpGrowth

Project Justification:

This includes a great technological change in TechUpGrowth to meet the competitive demands of the marketplace. The scope of the project would therefore encompass organization cybersecurity.

Product Characteristics and Requirements:

  • ERP System: The system should integrate all internal departments and processes, and it should provide current data and analytics in real-time.

  • Applications for Mobile Phones: In this application, there needs to be a user-friendly interface to engage the customer with more advanced features. This means personalized offers, customer support, and the creation of service tracks.

  • Cloud Migration: The company will migrate its data and applications to cloud services to achieve higher scalability and flexibility in operations.

  • Cybersecurity: This will be upgraded to protect sensitive data from being exposed and prevent unauthorized access.

Product User Acceptance Criteria:

  • ERP System: Only minor disruptions to the operating ERP system are to be expected when upgrading to better workflow and data integration.

  • Mobile Application: The mobile application should ensure well-established reviews amongst the consumers, with a resultant substantial rise in engagement in customer service within six months.

  • Cloud Infrastructure: The cloud system should work with zero downtime; through this, the data and applications should be accessed in the shortest time.

  • Controls and Cybersecurity: Issues of data breaches and system vulnerabilities should be reduced to a minimal quantity.

Summary of Project Deliverables

Project management-related deliverables:

Business case, project charter, scope statement, WBS, schedule, cost baseline, and final report.

Product-related deliverables: Fully operational ERP system, mobile application, cloud services, and upgraded cybersecurity infrastructure.



Task 4: Develop a work breakdown structure (WBS)

Work Breakdown Structure (WBS)

Date



Project Name: Digital Shift – TechUpGrowth



  • Main Category 1: Project Management

  • Sub-Category 1.1: Project Planning

  • Sub-Category 1.2: Budget Management

  • Sub-Category 1.3: Risk Management

  • Sub-Category 1.4: Stakeholder Communication


  • Main Category 2: Initiation

  • Sub-Category 2.1: Define Project Scope

  • Sub-Category 2.2: Assemble Project Team

  • Sub-Category 2.3: Conduct Technology Assessment



  • Main Category 3: Planning

  • Sub-Category 3.1: Develop Project Plan

  • Sub-Sub-Category 3.1.1: Detailed Timelines

  • Sub-Sub-Category 3.1.2: Resource Allocation

  • Sub-Category 3.2: Risk Assessment

  • Sub-Category 3.3: Stakeholder Engagement



  • Main Category 4: Execution

  • Sub-Category 4.1: ERP System Deployment

  • Sub-Sub-Category 4.1.1: Requirements Analysis

  • Sub-Sub-Category 4.1.2: System Design

  • Sub-Sub-Category 4.1.3: System Connection / Configuration Testing

  • Sub-Sub-Category 4.1.4: Integration and Testing

  • Sub-Sub-Category 4.1.5: Development

  • Sub-Category 4.2: Mobile Application Development

  • Sub-Sub-Category 4.2.1: Requirements Gathering

  • Sub-Sub-Category 4.2.2: Design and Prototyping

  • Sub-Sub-Category 4.2.3: Implementation

  • Sub-Sub-Category 4.2.4: Testing and Question & Answer

  • Sub-Sub-Category 4.2.5: Launching

  • Sub-Category 4.3: Cybersecurity Upgrades

  • Sub-Sub-Category 4.3.1: Risk Assessment

  • Sub-Sub-Category 4.3.2: Security Design

  • Sub-Sub-Category 4.3.3: Implementation

  • Sub-Sub-Category 4.3.4: Vulnerability Testing

  • Sub-Category 4.4: Cloud Migration

  • Sub-Sub-Category 4.4.1: Assess Current Infrastructure

  • Sub-Sub-Category 4.4.2: Plan Migration

  • Sub-Sub-Category 4.4.3: Execute Migration

  • Sub-Sub-Category 4.4.4: Post-Migration Testing



  • Main Category 5: Monitoring and Controlling

  • Sub-Category 5.1: Progress Tracking

  • Sub-Category 5.2: Performance Monitoring

  • Sub-Category 5.3: Issue Resolution

  • Sub-Category 5.4: Feedback Collection



  • Main Category 6: Closing

  • Sub-Category 6.1: Finalize Implementation

  • Sub-Category 6.2: Conduct Quality Assurance

  • Sub-Category 6.3: Provide Employee Training

  • Sub-Category 6.4: Project Handover

WBS Structure

Shape1



WBS Dictionary Entry

Date

Project Name: DigitalShift – TechUpGrowth

  • WBS Item Number: 4.1

WBS Item Name: ERP System Implementation

Description: The ERP implementation is part of the DigitalShift project. Its replacement will entail integrating a complete enterprise resource planning system that would smooth the operation of all internal processes, enhance access to data, and provide better insights for decision-making across all departments. The design of the ERP system should be done to retire legacy systems, reduce redundant workflows, and provide real-time analytics in support of strategic business operations. It will also cover the actual needs gathering, designing of the system, configuration, migration of data, and testing. The aim is for smooth integration with the existing IT infrastructure and the least disruption to the oncoming business activities.

  • WBS Item Number: 4.2

WBS Item Name: Mobile Application Development

Description: The mobile application development activity must be focused on developing a customer-centric app by enhancing user engagement with personalized experiences. It will also be able to provide real-time support and service accessibility, together with personalized offers. This covers the design, development, testing, and deployment of the application, considering compatibility with iOS and Android. The application will be incorporated with the backend company systems to ensure smooth customer interaction, whereby on each step, it will be gathering valuable user data for further improvement of customer service and marketing.

  • WBS Item Number: 4.3

WBS Item Name: Cybersecurity Upgrades

Description: The cybersecurity infrastructure of the company shall be brought up to an advanced level that will enable sensitive data protection from cyber threats. This will include advanced security protocols such as data encryption, multi-factor authentication, and intrusion detection systems (Ms Roopesh, 2024, p.38(1)). Regular security audits will be performed for the system to ensure that it is secure and at par with standard industry requirements. Training staff in this phase will also cover best practices in cybersecurity so that all employees can realize their role in securing the data.

  • WBS Item Number: 4.4

WBS Item Name: Cloud Migration

Description: The cloud migration activity involves moving information and applications of the company to the cloud. In so doing, there is increased scalability, flexibility, and cost efficiency. Major activities in this stage include selecting a cloud provider, migrating data, configuration of cloud services, and extending functionality and security testing (Kommisetty & Abhireddy, 2024, p. 26152(2)). The migration shall be done on a phase-by-phase basis to minimize disruption, and employees will also be trained on how these new cloud-based systems are managed and operated.

Part 3: Project Schedule Management

Task 5: Create a Gantt chart for WBS, and then identify at least five milestones

Team members Project Draft Schedule

 

 

 

Total hours->

216

184

208

187

220

1015

184

163

199

158

227

931

Major tasks

Start Date

End Date

Responsible

Estimated Hours per person

Total

Actual Hours

Total

 

 

 

 

A

B

C

D

E

Est. Hours

A

B

C

D

E

Act. Hours

1. Project Management

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

1.1 Project Planning

01-12-2024

28-02-2025

Alice

10

10

15

10

10

 

10

5

10

8

15

 

1.2 Budget Management

01-01-2025

28-02-2025

Jolly

3

4

4

6

5

 

3

5

4

5

10

 

1.3 Risk Management

01-01-2025

31-03-2025

Rojan

3

5

3

2

4

 

3

0

3

5

5

 

1.4 Stakeholder Communication

01-12-2024

31-03-2026

Team members

2

1

3

3

1

 

3

3

3

3

3

 

2. Initiation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

2.1 Define Project Scope

01-12-2024

31-12-2024

Jolly

5

3

2

10

4

 

5

5

6

2

10

 

2.2 Assemble Project Team members

01-12-2024

15-12-2024

Alice

5

10

4

6

5

 

5

5

5

5

10

 

2.3 Conduct Technology Assessment

16-12-2024

28-02-2025

Rojan

5

6

3

5

5

 

5

0

0

5

5

 

3. Planning

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

3.1 Develop Project Plan

01-03-2025

31-03-2025

Alice

5

5

8

6

10

 

5

5

6

10

8

 

3.1.1 Detailed Timelines

01-03-2025

31-03-2025

Jolly

5

10

5

5

5

 

0

5

5

0

10

 

3.1.2 Resource Allocation

01-03-2025

31-03-2025

Jackson

4

4

5

3

4

 

4

4

4

4

0

 

3.2 Risk Assessment

01-04-2025

30-04-2025

Rojan

8

4

8

4

4

 

0

4

0

8

8

 

3.3 Stakeholder Engagement

01-04-2025

31-05-2026

Alice

15

10

15

10

10

 

15

15

15

0

15

 

4. Execution

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.1 ERP System Implementation

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.1.1 Requirements Analysis

01-05-2025

31-05-2025

Rojan

6

5

0

5

0

 

5

5

6

0

0

 

4.1.2 System Design

01-06-2025

30-06-2025

Jackson

8

5

8

10

7

 

0

8

10

5

7

 

4.1.3 System Configuration

01-07-2025

31-07-2025

Morwin

10

10

0

0

10

 

10

10

10

0

0

 

4.1.4 Integration and Testing

01-08-2025

31-09-2025

Team members

10

10

10

10

10

 

12

12

12

12

12

 

4.1.5 Deployment

01-10-2025

31-10-2025

Jackson

5

5

10

0

5

 

5

5

5

10

0

 

4.2 Mobile Application Development

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.2.1 Requirements Gathering

01-05-2025

31-05-2025

Rojan

4

0

5

0

4

 

4

4

5

0

0

 

4.2.2 Design and Prototyping

01-06-2025

30-06-2025

Jackson

10

10

10

10

10

 

10

0

10

10

10

 

4.2.3 Development

01-07-2025

31-10-2025

Morwin

10

0

10

2

8

 

10

0

12

0

8

 

4.2.4 Testing and QA

01-11-2025

30-11-2025

Team members

5

4

5

6

5

 

5

5

0

5

0

 

4.2.5 Launch

01-12-2025

31-12-2025

Jackson

5

2

4

5

7

 

5

5

4

5

5

 

4.3 Cybersecurity Upgrades

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.3.1 Risk Assessment

01-05-2025

31-05-2025

Rojan

3

3

0

5

0

 

3

3

0

5

0

 

4.3.2 Security Design

01-06-2025

30-06-2025

Jackson

4

4

10

5

3

 

4

4

4

4

10

 

4.3.3 Implementation

01-07-2025

31-07-2025

Morwin

10

10

10

5

15

 

0

12

12

12

12

 

4.3.4 Vulnerability Testing

01-08-2025

30-08-2025

Team members

5

3

5

7

5

 

5

5

5

5

5

 

4.4 Cloud Migration

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

4.4.1 Assess Current Infrastructure

01-05-2025

31-05-2025

Rojan

5

5

0

0

0

 

5

5

0

0

0

 

4.4.2 Plan Migration

01-06-2025

30-06-2025

Jackson

5

5

5

5

5

 

5

0

5

0

5

 

4.4.3 Execute Migration

01-07-2025

30-08-2025

Morwin

10

0

10

0

0

 

10

0

10

0

0

 

4.4.4 Post-Migration Testing

01-09-2025

31-09-2025

Team members

5

5

5

5

5

 

5

0

5

5

0

 

5. Monitoring and Controlling

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

5.1 Progress Tracking

01-07-2025

31-05-2026

Alice

6

6

6

6

10

 

6

0

6

0

10

 

5.2 Performance Monitoring

01-07-2025

31-05-2026

Jolly

6

6

6

6

10

 

6

6

6

6

10

 

5.3 Issue Resolution

01-08-2025

31-05-2026

Rojan

6

6

6

6

12

 

6

10

6

0

12

 

5.4 Feedback Collection

01-09-2025

31-05-2026

Alice

3

3

3

9

12

 

0

3

0

9

12

 

6. Closing

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

6.1 Finalize Implementation

01-04-2026

30-04-2026

Jackson

5

5

5

10

10

 

5

5

5

10

10

 

6.2 Conduct Quality Assurance

01-05-2026

31-05-2026

Team members

15

15

15

15

15

 

10

15

20

25

30

 

6.3 Provide Employee Training

01-05-2026

31-05-2026

Alice

5

5

5

5

5

 

5

5

5

5

5

 

6.4 Project Handover

01-05-2026

31-03-2026

Team members

15

15

15

15

15

 

15

15

15

15

15

 

Part 4: Project Cost and Quality Management

Task 6: Develop documents for cost estimate and business case financial analysis

Cost Estimate

Project Name: DigitalShift

 

Date: 10-09-2024

 

 

 

 

 

 

 

 

Labour

Internal

$/hour

Internal

External

$/hour

External

Total

Non-labor $

Total Cost

WBS Categories

Hours

Labor

 

$ Total

Labor

 

$ Total

Labor

 

 

1. Initiating

500

400

$100

$ 40,000

250

$ 110

$ 27,500

$ 67,500

$ 2,58,000

$ 3,25,500

2. Planning

500

200

$80

$ 16,000

150

$ 105

$ 15,750

$ 31,750

$ 3,44,250

$ 3,76,000

3. Executing

 

 

 

 

 

 

 

 

 

 

3.1 ERP Implementation

1,100

500

$95

$ 47,500

400

$120

$ 48,000

$ 95,500

$ 23,73,000

$ 24,68,500

3.2 Mobile App Development

1000

700

$85

$ 59,500

600

$130

$ 78,000

$ 1,37,500

$ 17,05,500

$ 18,43,000

3.3 Cybersecurity Upgrades

500

300

$90

$ 27,000

100

$95

$ 9,500

$ 36,500

$8,63,000

$ 8,99,500

3.4 Cloud Migration

400

250

$90

$ 22,500

200

$120

$ 24,000

$ 46,500

$5,49,000

$ 5,95,500

3.5 Employee Training & Change Management

400

200

$100

$ 20,000

300

$150

$ 45,000

$ 65,000

$9,05,000

$ 9,70,000

4. Monitoring and Controlling

200

100

$95

$ 9,500

100

$ 130

$ 13,000

$ 22,500

$2,53,500

$ 2,76,000

5. Closing

800

500

$100

$ 50,000

150

$ 140

$ 21,000

$ 71,000

$1,80,000

$ 2,51,000

Subtotal

 

 

 

$ 2,92,000

 

 

$2,81,750

$ 5,73,750

$ 74,31,250

$ 80,05,000

Reserves

 

 

 

 

 

 

 

 

 

$20,00,000

Total

 

 

 

 

 

 

 

 

 

$ 1,00,05,000

 

 

 

 

 

 

 

 

 

 

 

Assumptions

1. Labor rates have been adjusted upward to reflect a higher total project cost.

2. Non-labor costs include software, hardware, and other infrastructure expenses.

3. The project's benefits increase significantly over time due to improved efficiency, customer engagement, and operational cost savings.

4. The discount rate remains at 8%, in line with standard financial practices.





Part 5: Project Resource Management

Task 7: Prepare a Responsibility Assignment Matrix (RACI Chart) for the WBS















RACI MATRIX

PROJECT DETAILS






 

 






PROJECT No:

MA-015-02






DATE:

 






FULL PROJECT NAME:

Project Digital Shift






PROJECT MANAGER:

Group Leader






RACI

Task

Project Manager

IT Systems Architect

Mobile App Developer

Cybersecurity Specialist

Cloud Solutions Engineer

Change Management Consultant

1. Project Management

 

 

 

 

 

 

1.1 Project Planning

A

I

C

C

R

C

1.2 Budget Management

A

C

C

R

C

A

1.3 Risk Management

A

C

R

C

C

C

1.4 Stakeholder Communication

A

I

I

I

I

C

2. Initiation

 

 

 

 

 

 

2.1 Define Project Scope

A

C

I

C

R

C

2.2 Assemble Project Team

R

A

C

R

C

I

2.3 Conduct Technology Assessment

A

R

C

C

R

C

3. Planning

 

 

 

 

 

 

3.1 Develop Project Plan

R

A

C

I

C

C

3.2 Risk Assessment

A

R

C

C

C

I

3.3 Stakeholder Engagement

R

C

I

I

I

R

4. Execution

 

 

 

 

 

 

4.1 ERP System Implementation

 

 

 

 

 

 

4.1.1 Requirements Analysis

A

R

A

C

I

C

4.1.2 System Design

A

R

C

C

C

C

4.1.3 System Configuration

C

R

C

I

A

A

4.1.4 Integration and Testing

A

R

A

C

C

C

4.1.5 Deployment

A

R

I

C

C

I

4.2 Mobile Application Development

 

 

 

 

 

 

4.2.1 Requirements Gathering

I

C

R

I

C

R

4.2.2 Design and Prototyping

A

C

R

C

C

A

4.2.3 Development

C

I

A

C

A

C

4.2.4 Testing and QA

A

C

R

A

C

C

4.2.5 Launch

A

I

A

C

R

I

4.3 Cybersecurity Upgrades

 

 

 

 

 

 

4.3.1 Risk Assessment

A

C

A

R

C

R

4.3.2 Security Design

R

C

C

A

R

C

4.3.3 Implementation

A

R

C

R

C

A

4.3.4 Vulnerability Testing

I

A

I

A

I

C

5. Monitoring and Controlling

 

 

 

 

 

 

5.1 Progress Tracking

R

I

A

C

C

A

5.2 Performance Monitoring

A

C

I

C

A

C

5.3 Issue Resolution

R

C

C

I

C

C

5.4 Feedback Collection

A

A

C

C

I

R

6. Closing

 

 

 

 

 

 

6.1 Finalize Implementation

A

R

C

C

A

C

6.2 Quality Assurance

C

R

I

R

C

I

6.3 Employee Training

A

I

C

A

C

R

6.4 Project Handover

I

R

A

C

C

C

6.5 Celebration

A

C

I

C

R

A



Part 6: Project Risk Management

Task 8: Create a risk register

Risk Register for Digital Shift

Date

Project Name: Digital Shift

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

ID No.

Rank

Risk Name

Risk Description

Category

Root Cause

Triggers

Potential Responses

Risk Owner

Probability

Impact

Status

1

High

ERP System Implementation Delays

Hold up the implementation of the ERP system

Technical

system integration Complexity

Vendor delays, technical issues

Enhancing the Phase of testing, Compromise the schedule, working nearly with the vendor

IT Systems Architect

High

High

Open

2

High

Mobile App Development Delays

Hold up the development of the mobile application

Technical

Unforeseen development challenges

Development team issues, changes of scope management

Maintain project timeline, Enhancing resources, Efficitively check-ins

Mobile App Developer

Medium

High

Open

3

Medium

Cybersecurity Breaches

Breaks in cybersecurity Calculate

Security

Inadequate security measures

System susceptibility, Additional threats

Develop Enhancing security protocols, regular Check-up

Cybersecurity Specialist

Medium

High

Open

4

Medium

Cloud Migration Issues

Problems during the move to cloud-based solutions

Technical

Compatibility issues

Cloud issues, deployment problems

Planning of phased migration, planning of backup

Cloud Solutions Engineer

Medium

Medium

Open

5

High

Budget Overruns

Increasing the allocated project budget

Financial

Unpredicted costs, poor budgeting

Cost Enhance, changes of scope

Budget analyzing, Regularly funds

Project Manager

Medium

High

Open

6

Medium

Resistance to Change

Employee resistance to new changes

Organizational

Slow purchase rate, poor communication

Feedback from Staff members, Decreasing adoption rates

Organise workshop for change management, Frequent communication

Change Management Consultant

High

Medium

Open

7

Medium

Inadequate Stakeholder Engagement

Insufficient engagement with stakeholders

Stakeholder

Poor communication strategies

Deploy of feedback, Unadjustment

Continue meetings of Stakeholders, Modify reports

Project Manager

Medium

Medium

Open

8

Medium

Technical Skill Gaps

Gaps in technical skills within the team

Organizational

Poor training experience

Performance problems, project hold-up

Conduct additional training, consultants hiring

Project Manager

Medium

Medium

Open

9

Low

Data Migration Errors

Errors occurring during data migration

Technical

Incorrect data Modifying

Data Changes, Errors in system

Development through data Verification & validation processes

IT Systems Architect

Low

High

Open

10

Low

Legal or Compliance Issues

Issues related to legal or regulatory compliance

Compliance

Continuous changes or oversee

New rules and terms, Failures issues

continue the Right reviews, upgrade policy

Project Manager

Low

Medium

Open


Task 9: Plot the risks on a Probability/Impact Matrix

Summary

The DigitalShift project is a unique approach to renovating the operations of TechUpGrowth with a competitive advantage over the rest of the players in technology. This will involve the implementation of an ERP system, customer-centric mobile app development, cybersecurity upgrade, and migration to cloud infrastructure. Simultaneously, this shall be aligned with internal process streamlining and improvement in customer engagement. Complete employee training will also ensure successful new system adoptions. Starting with the 18-month timeline to present-the schedule to complete-and the $10M budget, the projected long-term return for the investment includes a projection of a 44% on-investment return, greater scalability, flexibility, and data security. This would be for the overall company.



References

Khodurska, M. 2020. Methods and tools to ensure information security in aviation enterprises, pp. 1-135, https://dspace.nau.edu.ua/bitstream/NAU/42664/1/%D0%A4%D0%A2%D0%9C%D0%9B_2020_275_%D0%A5%D0%BE%D0%B4%D1%83%D1%80%D1%81%D1%8C%D0%BA%D0%B0_%D0%9C.%D0%84..pdf

?Kommisetty, P. D. N. K., & Abhireddy, N 2024. Cloud Migration Strategies: Ensuring Seamless Integration and Scalability in Dynamic Business Environments. International Journal of Engineering and Computer Science13(04), 26146–26156. https://doi.org/10.18535/ijecs/v13i04.4812

Roopesh, Ms 2024. CYBERSECURITY SOLUTIONS AND PRACTICES: FIREWALLS, INTRUSION DETECTION/PREVENTION, ENCRYPTION, MULTI-FACTOR AUTHENTICATION. 4(3), pp.37–52. https://doi.org/10.69593/ajbais.v4i3.90

Soubra, L. 2021. BIG DATA. CUSTOMER CENTRICITY and SUSTAINABILITY in the BANKING INDUSTRY, BAU Journal, 3(1), pp.1-11. https://doi.org/10.54729/2789-8334.1067

?



Appendix

MEETING AGENDA

Meeting/Project Name:

DigitalShift Kick-off

Date of Meeting: (MM/DD/YYYY)

08/06/2024

Time:

10:00 AM

Meeting Facilitator:

Olivia, Project Manager

Location:

TechUpGrowth Headquarters, Conference Room A



1. Meeting Objective

This is provide effectiveness of techupgrowth project toward managing digital project.



2. Attendees

Name

Department/Division

E-mail

Phone


Project Management




IT Systems Architect




Cybersecurity




Change Management




Mobile App Development





3. Meeting Agenda

Topic

Owner

Time

Project Overview and Scope

Olivia

10:00 AM

Roles and Responsibilities

Olivia

10:30 AM

Technology Assessment

Beatrice

11:00 AM

Timeline and Milestones

Olivia

11: 30PM

Q&A Session

All

12:00 PM



4. Pre-work/Preparation (documents/handouts to bring, reading material, etc.)

Description

Prepared by

Project Charter

Olivia

Technology Assessment Report

Beatrice





MEETING MINUTES

Meeting/Project Name:

DigitalShift Kick-off

Date of Meeting: (MM/DD/YYYY)

06/10/2024


Time:

10:00 AM

Minutes Prepared By:

Sarah Johnson

Location:

TechUpGrowth Headquarters, Conference Room A

1. Meeting Objective

Official project start and discussion of scope, team roles, and key deliverables.

2. Attendance at Meeting

Name

Department/Division

E-mail

Phone


Project Management




IT Systems Architect




Cybersecurity




Change Management




Mobile App Development





3. Agenda and Notes, Decisions, Issues

Topic

Owner

Time



Project Overview and Scope


10:00 AM

Roles and Responsibilities





10:30 AM




Technology Assessment



11:00 AM

Timeline and Milestones


11:30 AM

4. Action Items

Action

Owner

Due Date

Submit final technology assessment



Finalize project timeline



5. Next Meeting (if applicable)

Date: (MM/DD/YYYY)

09/01/2024

Time:

10:00 AM

Location:

TechUpGrowth Headquarters

Objective:



Review and finalize the project timeline and assign resources





47 | Page


FAQ's